Works on the segment of the motorway Е-763 from New Belgrade to Surčin in the length of 7.9 km are in full swing.
Execution of preliminary works on the segment of the sub-section 1 from km 3+075 tо km 5+575 is in progress. Works on marking of the road, cleaning of the terrain with removal of shrubbery, undergrowth and trees, excavation of humus, excavation of soil and construction of embankment out of sandy materials, as well as geodetic and preliminary works on the reconstruction of reclamation canals are being executed.
The state road, section New Belgrade – Surčin, located on the left bank of the river Sava, has been designed for the overall speed of 80 km/h, with mild longitudinal slopes and, when it is completed, it will represent the shortest link between the city of Belgrade and the motorway Е-763 (“Miloš Veliki“).