Due to the constant increase in traffic in the Republic of Serbia, as well as the increasing share of electronic toll collection in the total traffic through toll stations, PE "Roads of Serbia" launched the Project to expand 26 toll stations in the Republic of Serbia.
Works on the expansion of the Kolari, Jagodina, Aleksinački Rudnici, Ćuprija toll stations are underway, as well as works in the preparatory phase on the expansion of the Markovac toll station.
TS Kolari - works are underway on the construction of the administrative building and canopy. The remaining works are on the construction of the concrete road and the installation of the toll system equipment, as well as traffic signals.
TS Jagodina - the second phase of expansion is in progress, works are being carried out on the construction of the pavement structure and hydrotechnical works. In the first phase of the works, a new administrative building was completed and moved in, a canopy was built and traffic was opened through the extended part.
TS Aleksinački Rudnici - finishing works are underway inside the new administrative building on the canopy, after which the final layers of the roadway construction will be made.
TS Ćuprija on the right - works on the construction of embankment layers and roadway construction, storm drains, reinforced concrete works, works on relocation and placement of installations are in progress.
In the previous period, the works on the toll stations Paraćin and Ražanj were completed.
You can watch the video at: 10.07.24. Projekat proširenja naplatnih stanica